About Company
Staff and structure
As of 1.8.2008, the company had 70 employees, of which:
- Administration and technical staff 8
- Assembly shop 1 + 29
- Shop group 1 + 25
- Electric group 1 + 2
- Welding school 1 + 2
Company objectives 2008
- Turnover of CZK 40 million, of which:
- Assemblies and repairs CZK 20 million
- Fabrication CZK 17.5 million
- Welding school CZK 1.5 million
- Business activities CZK 1 million
- Gross profit CZK 3 million
- The target number of employees as of 31.12.2008 - 70.
- Implementing ISO 9001
Key business partners
- ČEZ, a.s.
- DALKIA Česká Republika a.s.
- AmplusServis a.s.
The business partners above make up 75% of the company turnover.
Important projects and references
- Production and assembly of steel constructions for GSM transmitters for KORAS TRADE s.r.o. and Teplotechna Ostrava, contract worth CZK 6.5 mil.
- Production of steel constructions for a chair lift for Transmisie s.r.o., contract worth CZK 1.2 mil.
- Production of chain feeders and their cases, ČEZ, a.s. (EDĚ), yearly contract worth CZK 2 million
- Replacement of hydrants in EDĚ, contract worth CZK 3.2 million
- Disassembly and assembly of steel halls for Dexon a.s., PROGIS s.r.o., contracts worth CZK 1.6 and 3 million
- Major overhaul of chain feeders in EDĚ, yearly contract worth CZK 3.5 million
- Major overhaul of boilers and mills for AmplusServis a.s., yearly contract worth about CZK 1 million
2008
![]() |
Realization of piping in the project of Desulphurization of Tušimice Power Plant Contract worth about CZK 3 million; references available from: Ing. Bromek - GASCONTROL a.s., phone no.: ...
2008
![]() |
Supplies of steel constructions for REMO Velký Manesmann VT TŽ a.s. Contract worth about CZK 9 million; references available from: Bronislav Zawada - Třinecký inženýring a.s., phone ...
1.6.2008
![]() |
Energetika Třinec, a.s Production and assembly of steel constructions for GSM on the chimney belonging to Energetika Třinec, a.s.skeleton ...